NSTA: £40Bn forecast spend on UK North Sea decommissioning

Rising costs, extended field production and new developments have increased the forecast capex for decommissioning oil and gas facilities offshore the UK to £40Bn (US$51Bn).

This decommissioning cost estimate is up from the £37Bn (US$47Bn) forecast in November 2022, as developments are added and costs for vessels, drilling rigs and specialist equipment have risen.

The North Sea Transition Authority (NSTA) forecast around £17Bn would be spent on well decommissioning in its latest report, up £1Bn from its previous estimate. £9Bn would be spent on platform removals, £4.5Bn on subsea infrastructure, £3Bn on recycling, site remediation and monitoring and £6Bn on what NSTA calls owners costs.

News article on 18 August 2023 by Martyn Wingrove from rivieramm.com


For further reading, please visit rivieramm.com >> NSTA: £40Bn forecast spend on UK North Sea decommissioning